Header Ads Widget

Ticker

6/recent/ticker-posts

Thumb rule used in Construction Industry !!


There are endless thumb rule used in Construction Industry , I am stating few of them listed below : -

Concrete : 0.038 cum per sq. ft. of plan area. 
                  (+/- 5%)

Steel : 4.50 to 5.00 Kg per sq. ft.

Shuttering : 2.40 to 2.50 times the plan area of slab (this includes col./beams/sides etc)

Brick Work : 0.015 cum per sq. ft. of plan area.

Approximately 0.25 cubic metres of mortar and 500 bricks are required for 1 cubic metre of brickwork

Concrete: 0.5A Cum for Commercial Bldg.
              0.2A Cum for Residential Bldg.

Where, A= Total Built Up Area.(i.e. Plinth Area xNo. of Floor)

Steel: 4.5-4.75 kg per Sqft of Built up Area for Residential Building

     5.0-5.5 kg per Sqft of Built up area for                 Commercial Building.


Formwork


(1). Shuttering = 6 times the quantity of concreting.(or2.4 times the plinth area)

(a) No of12 mm Ply (2.44mx1.22m)=0.22 times of shuttering ( or, 0.4A)

(b)Batten(75mmx40mm)=19.82X No. of Ply Sheets(it gives batten in RM)

(c)Nails=0.22x total area of shuttering.(unit-kg) Practically, 75 gm nails and 75 gm binding wire + nut-bolts are consumed per sqm of shuttering

(d)Shuttering Oil=0.065x total area of shuttering(unit-Lt)

Electrical cost = Rs 133/sft

Plumbing cost = Rs 126/sft

Fire fighting cost = Rs 40/sft

External development = Rs 94.5/sft

Labour Productivity:

Brick Work - 1 mason + 1Labour = 1.25 cm

Wall Plastering - 1 mason +1 Labour = 10 Sqm

Ceiling Plastering - 1 mason + 1Labour = 8 Sqm

External Plastering - 1 mason + 1 Labour = 8 Sqm

Carpenter - 1 Skilled + 1 Un skilled = 4 Sqm

Bar bender - 1 Skilled + 1 Un skilled = 200 Kg

Tile work - 1 Mason + 1Labour = 10 Sqm

Painter - Skilled -OBD 600 Sft

                - Emulsion 800 Sft

CO-EFFICIENT FOR PAINTING:

Partly paneled and glazed doors = 0.80 times the door or window area.

Collapsible gates = 1.50

Corrugated sheeted steel doors = 1.25

Rolling shutters = 1.10

Expanded metal hard drawn steel = 1.00

Fencing and gates, brace, rails = 1.00

Flush doors = 1.20

Partly paneled doors = 1.00

Fully glazed doors = 0.80

Fully louvered = 1.80

I f its only for slab ….then a 5″ slab almost costs roughly Rs.220/- per sq. Feet all inclusive of Steel, Rcc, Shuttering etc.

If u are asking for residential building complete in all respects…than it costs u around Rs. 1200/- per sq. Feet. Civil Structure Work – Rs. 750 per sqft and for Finishing Work – Rs. 450 per sqft.

(a) Painting - Rs 12 - 17 per sqft (two layers of putty + two layers of coat) including taxes

(b) Flooring - Marble is Rs 80 per sqft (depends on the type of marble may be - but this is what it is costing us). Granite and bathroom tiles 15 - 20 Rs per sqft (we provide all material such as cement, sand etc).

(c) Electrical - You are better off buying the materials for them. A rough guide is Rs 50 - 100 per sqft for materials and Rs 12 - 20 per sqft for labor.



CEMENT REQUIREMENTS:

M10 : 210 Kg

M20 : 320 Kg

M25 : 340 Kg

M30 : 380 Kg

M35 : 410 Kg

M40 : 430 Kg

M45 : 450 Kg

I hope these thumb rule will help you in your career

Post a Comment

0 Comments